Sr. No. | List | |
---|---|---|
REVIEW/ QUERIES ON DOCUMENTS RECEIVED FROM CLIENT/ PROCESS LICENSOR | ||
1. | Basic/ Extended basic engineering package | |
– Project design basis | ||
– Piping design basis | ||
– P & I D | ||
– Equipment data sheet | ||
– Piping material specification | ||
– Review the entire package requirement and generate queries for missing information, contradicting information, Ambiguous information, and content of information. | ||
2. | Site survey drawing and Site master plan | |
3. | Client’s/ Process Licensor’s design standards | |
4. | Existing facility documentation | |
5. | Scope of work and Split of work | |
6. | Applicable codes and Standards | |
7. | Review requirement | |
8. | Project schedule | |
9. | Documentation requirement | |
10. | Design basis for stress analysis and support design | |
11. | Design basis for 3D model/ Usage of software | |
12. | Local regulation and Statutory requirement | |
Sr. No. | List | |
DESIGN | ||
1. | Client’s standard/ preference for locating various facilities on the plot. | |
2. | Client’s standard/ preference for equipment spacing. | |
3. | Minimum foundation heights for equipment and supports | |
4. | Preference of piperack/ Pipe sleepers design if any, | |
– Preference of elevated rack v/s pipe sleepers v/s inside trench v/s buried pipes and extent of the same | ||
– Concrete, steel or combination of both | ||
– Minimum piperack elevation in general and at road/ rail crossing | ||
– Tier to tier distance | ||
– Spare space in each tier for future expansion | ||
– Cable tray/ duct routing preference – combined pipes and cables tier or separate? | ||
– Walkways between cable trays for cable pulling/ maintenance | ||
– Location of rack longitudinal beam at tier elevation or in between tier elevation. | ||
– Conventional rack or modular rack. If modular, philosophy of design, erection etc. | ||
– Incase of air fin cooler on top of the rack, operating/ maintenance platform requirement and access | ||
– Incase of equipment supported on top of the rack, maintenance requirement, erection methods etc. | ||
– Cable tray layout – flat type of tree type | ||
– Usage of Low friction rods, low friction sliding plates etc. | ||
– Movement requirement below the racks | ||
5. | Preference on Building/ structure design | |
– Concrete, steel, combination of both | ||
– Building sides closed or open. If closed type of enclosure with doors windows, cladding etc. | ||
– Minimum floor to floor height requirement | ||
– Minimum ground floor plinth elevation requirement | ||
– Roof configuration | ||
– Floor finishes – Type of floor | ||
– Encasement of steel sections | ||
– Floor and wall cut out type – precast or at site, with or without sleeves, sealed or unsealed etc. | ||
– Floor drainage philosophy | ||
– Need for foundation for small equipment or can be supported off the floor | ||
– Extent of paving out side building | ||
– Architectural features if any | ||
– Expansion requirement/ future space/ provision to be made at present for any future requirement. | ||
– Equipment erection philosophy within building | ||
– Preference on equipment support and mounting arrangement. | ||
6. | Layout consideration | |
– Specific hazard consideration | ||
– Maintenance requirement such as crane, monorail, lifting beams etc. | ||
– Road width, roads cross-section and type of road etc. | ||
– Future expansion provision and consideration | ||
– Operating access requirement for instrument valves manways, handholes etc. | ||
– Storage warehouse sizes, no. of days storage for raw material, intermediate, finished product, waste, by products etc. and their loading and unloading consideration” | ||
– Non plant facilities requirement | ||
– Extent of paving, drainage requirements and containment consideration. | ||
– Architectural consideration | ||
– Equipment erection consideration for very heavy, very tall and fragile equipment. | ||
– Understanding operating and maintenance requirement for the entire plant and individual equipment | ||
7. | Stress analysis | |
– Stress analysis design basis | ||
– Derivation procedure/ criteria for stress critical line list | ||
– Design codes to be used | ||
– Wind loading data and earthquake zone | ||
– Additional external loading consideration such as snow load, solar effect etc. | ||
– Fabricated equipment acceptable equipment nozzle loads for various sizes and pound rating nozzles | ||
– Proprietary/ Rotary equipment acceptable equipment external nozzle loading for equipment such as pumps, turbines, compressors, air fin coolers, fired heaters etc | ||
– Package equipment battery limit tie in point acceptable nozzle loading | ||
– Relief valve force calculation – client’s standard | ||
– Software to be used for stress analysis. | ||
– Documentation requirement. | ||
– Review requirement by client | ||
8. | Pipe support design | |
– Movement | ||
– Design criteria, guidelines, support standard. | ||
– Up to what size it is supported on design office document and below which size to be field supported | ||
– Structural steel section type. | ||
– Specific requirement of using type of support | ||
– Loading/ height criteria for determining whether to be built by civil group or piping group. | ||
– Probable vendor for spring | ||
– Usage of low friction slide plates in supports near critical equipment, high expansion area etc | ||
– Vessel supported pipes – cleat, standard, design | ||
– Documentation requirement :
Pipe support on model – annotation or actual support Pipe support on isometrics or on layout Support MTO Support design software |